Which sequence correctly describes the grounding procedure for a unit substation?

Study for the Low Voltage Qualification Test. Explore flashcards and multiple-choice questions with hints and explanations for each, ensuring thorough preparation!

Multiple Choice

Which sequence correctly describes the grounding procedure for a unit substation?

Explanation:
Working safely on a unit substation requires isolating the equipment from all energized sources before applying any grounding. First remove the load to stop energy from flowing to downstream circuits. Then fully isolate the unit from the source by opening the protective devices in the sequence that guarantees complete de-energization of the feeder—first the circuit breakers, then the load-break switch or fuse arrangement. Once the circuit is confirmed de-energized, apply grounding on the line side of the fuse to bleed any voltage present on that side, then on the load side of the fuse to equalize the downstream side, and finally ground the secondary bus to ensure the entire internal bus is at earth potential. This order minimizes the chance of backfeed or hazardous voltage during work and provides a known zero-energy condition. Other sequences that ground before complete isolation or place grounds on the wrong side can leave energized parts or create unsafe voltage differences.

Working safely on a unit substation requires isolating the equipment from all energized sources before applying any grounding. First remove the load to stop energy from flowing to downstream circuits. Then fully isolate the unit from the source by opening the protective devices in the sequence that guarantees complete de-energization of the feeder—first the circuit breakers, then the load-break switch or fuse arrangement. Once the circuit is confirmed de-energized, apply grounding on the line side of the fuse to bleed any voltage present on that side, then on the load side of the fuse to equalize the downstream side, and finally ground the secondary bus to ensure the entire internal bus is at earth potential. This order minimizes the chance of backfeed or hazardous voltage during work and provides a known zero-energy condition. Other sequences that ground before complete isolation or place grounds on the wrong side can leave energized parts or create unsafe voltage differences.

Subscribe

Get the latest from Passetra

You can unsubscribe at any time. Read our privacy policy